Features:
Target DCUT (code complete) date: Mon. Jan. 20
Target release date: Fri. Jan. 24
Line item | Volunteer | Sizing | Timeframe | Status |
---|---|---|---|---|
DOM L3 | ||||
DOM Configuration | Elena Litani | 1 pw | Dec. 2 - 6 | Complete |
ID Attributes | Elena Litani | 1 pw | Dec. 16-20 | Complete |
normalizeDocument | Elena Litani | 1 pw | Dec. 9-13 | Complete |
TypeInfo and general changes | Elena Litani | 1 pw | Jan. 13 - 17 | Complete |
compareTreePosition changes | Lisa Martin | 1 pw | Jan. 13 - 17 | Complete (except for document ordering, which will be done in 2.3.1) |
XML 1.1 and Namespaces 1.1 | ||||
Basic support for 1.1 | Neil Graham | 2.5 pw | Nov. 25 - Dec. 11 | Complete |
Serializer changes | Neil Graham | 1.5 pw | Jan. 8-17 | Complete |
Namespaces 1.1 | Neil Graham | .5 pw | Dec. 9 - 13 | Complete |
XML Schema Errata | ||||
Investigate changes to be made | Sandy Gao | 3 pd | To be completed by Jan. 8 | Ongoing, as XML Schema WG has not posted final errata. To be completed in Xerces 2.3.1 |
Changes for errata | Sandy Gao | 2 pw | Dec. 9 - Jan. 17 | In progress. To be completed in Xerces 2.3.1. |
Performance enhancements | ||||
Scanner enhancements | Elena Litani | 2 pw | Nov. 19 - 29 | Will be completed in Xerces 2.3.1 |
DTM for schema processing | Sandy Gao | 2 pw | Dec. 2 - 20 | Complete |
JAXP 1.2 | ||||
Misc. cleanup | Neil Graham | .5 pw | Jan. 6 - 8 | Complete |
Miscellaneous | ||||
Build work for commons | Neil Graham | 1 pw | Dec. 9 - 20 | Complete |
Strict uri feature | Sandy Gao | 1 pw | Dec. 16 - Jan. 10 | Complete |
Security feature | Neil Graham, Neeraj Bajaj et. al | 1 pw | Dec. 16 - Jan. 10 | Complete |
XNI changes | Elena Litani, Andy Clark et. al | 1 pw | Dec. 16 - Jan. 10 | Complete |
DCUT | Jan. 20 | Jan. 27 (actual) | ||
Build and publish Xerces 2.1 | Week of Jan. 20 |