Features:
Target DCUT (code complete) date: July 26
Target release date: Week of Aug. 20
Line item | Volunteer | Sizing | Timeframe | Status |
---|---|---|---|---|
DOM L3 | ||||
Text | Elena Litani | 1 pw | June 17 - June 21 | |
Load and Save | Elena Litani | 1 pm | June 24 - July 19 | |
PSVI | ||||
Provide access from DOM | Sandy Gao | 1 pm | June 17 - July 12 | |
XML 1.1 | ||||
Implement XML 1.1 | Neil Graham | 1 pm | June 17 - July 12 | |
Misc. features and cleanup | ||||
Features TBD - see candidate list below | Neil Graham, Lisa Martin, Sandy Gao | July 15 - July 26 | ||
Performance enhancements | ||||
Misc. performance-related items (TBD) | Gopal Sharma, Neerja Bajaj, Rahul Srivastava, Pavani Mukthipudi, et. al | TBD | TBD | |
DCUT | July 26 | |||
Bug fix, test, etc. | all | 3 pw | July 29 - Aug. 17 | |
Build and publish Xerces 2.1 | Week of Aug. 20 |