Features:

Target DCUT (code complete) date: Mon. Jan. 20

Target release date: Fri. Jan. 24

Development line items

Line item Volunteer Sizing Timeframe Status
DOM L3
DOM Configuration Elena Litani 1 pw Dec. 2 - 6 Complete
ID Attributes Elena Litani 1 pw Dec. 16-20 Complete
normalizeDocument Elena Litani 1 pw Dec. 9-13 Complete
TypeInfo and general changes Elena Litani 1 pw Jan. 13 - 17 Complete
compareTreePosition changes Lisa Martin 1 pw Jan. 13 - 17 Complete (except for document ordering, which will be done in 2.3.1)
XML 1.1 and Namespaces 1.1
Basic support for 1.1 Neil Graham 2.5 pw Nov. 25 - Dec. 11 Complete
Serializer changes Neil Graham 1.5 pw Jan. 8-17 Complete
Namespaces 1.1 Neil Graham .5 pw Dec. 9 - 13 Complete
XML Schema Errata
Investigate changes to be made Sandy Gao 3 pd To be completed by Jan. 8 Ongoing, as XML Schema WG has not posted final errata. To be completed in Xerces 2.3.1
Changes for errata Sandy Gao 2 pw Dec. 9 - Jan. 17 In progress. To be completed in Xerces 2.3.1.
Performance enhancements
Scanner enhancements Elena Litani 2 pw Nov. 19 - 29 Will be completed in Xerces 2.3.1
DTM for schema processing Sandy Gao 2 pw Dec. 2 - 20 Complete
JAXP 1.2
Misc. cleanup Neil Graham .5 pw Jan. 6 - 8 Complete
Miscellaneous
Build work for commons Neil Graham 1 pw Dec. 9 - 20 Complete
Strict uri feature Sandy Gao 1 pw Dec. 16 - Jan. 10 Complete
Security feature Neil Graham, Neeraj Bajaj et. al 1 pw Dec. 16 - Jan. 10 Complete
XNI changes Elena Litani, Andy Clark et. al 1 pw Dec. 16 - Jan. 10 Complete
DCUT Jan. 20 Jan. 27 (actual)
Build and publish Xerces 2.1 Week of Jan. 20

Candidate features and cleanup items (if time permits)