Xerces 2.1 Plan

Features:

Target DCUT (code complete) date: July 26

Target release date: Week of Aug. 20

Development line items

Line item Volunteer Sizing Timeframe Status
DOM L3
Text Elena Litani 1 pw June 17 - June 21
Load and Save Elena Litani 1 pm June 24 - July 19
PSVI
Provide access from DOM Sandy Gao 1 pm June 17 - July 12
XML 1.1
Implement XML 1.1 Neil Graham 1 pm June 17 - July 12
Misc. features and cleanup
Features TBD - see candidate list below Neil Graham, Lisa Martin, Sandy Gao July 15 - July 26
Performance enhancements
Misc. performance-related items (TBD) Gopal Sharma, Neerja Bajaj, Rahul Srivastava, Pavani Mukthipudi, et. al TBD TBD
DCUT July 26
Bug fix, test, etc. all 3 pw July 29 - Aug. 17
Build and publish Xerces 2.1 Week of Aug. 20