Xerces-2 Schema beta

Features:

Target DCUT (code complete) date: Nov. 30

Target release date: late December

Open Issues:

Clean-up work. Needs volunteers.

Features to be implemented if time permits

Development line items

Line item Volunteer Sizing Target start Target completion Status
New simpleType design Neeraj Bajaj (Sandy Gao) 2 pm Sept. 15 Nov. 16
Particle Derivation restriction checking Lisa Martin 2-3 pw Nov. 1 Nov. 23
cos-element-consistent checking Lisa Martin 1 pw Nov. 26 Nov. 30
UPA checking and subsitution group handling Sandy Gao 2 pw Nov. 1 Nov. 16
PSVI support
  • XNI changes
  • gather information and pass thru XNI
  • expose PSVI to app
Elena Litani, Sandy Gao, Arun Yadav 4 pw (elapsed) Nov. 1 Nov. 30
DOM L3 serialization Rahul Srivastava 3 pw Nov. 1 Nov. 23
Misc. DOM L3 features:
  • Load (2 pw)
  • Pre-parsing schemas (1 pw)
  • Misc. DOM L3 Core features - TBD
Gopal Sharma, Pavani Mukhtipudi Nov. 1 Nov. 30
Grammar caching
  • grammar resolution
  • schemaLocation feature?
Neil Graham 3-4 pw Nov. 1 Nov. 30
Testing all 2 weeks (elapsed) Dec. 3 Dec. 14
Build all Week of Dec. 17 Week of Dec. 17