NiFi Status
NiFi Project Incubation Status

This page tracks the project status, incubator-wise. For more general project status, look on the project website.

The Apache NiFi project graduated as a TLP on July 15th 2015

The NiFi project graduated on 2015-07-15

Description

Apache NiFi is an easy to use, powerful, and reliable system to process and distribute data.

News
Project info
item type reference
Website www http://nifi.incubator.apache.org/
Mailing list dev dev@nifi.incubator.apache.org
. commits commits@nifi.incubator.apache.org
. users users@nifi.incubator.apache.org
Issue tracking . https://issues.apache.org/jira/browse/NIFI/
Source code Git https://gitbox.apache.org/repos/asf/incubator-nifi.git
Source code Git (Mirror) https://github.com/apache/incubator-nifi
Source code (for web site) SVN https://svn.apache.org/repos/asf/incubator/nifi/
Mentors billie Billie Rinaldi
. arvind Arvind Prabhakar
. wikier Sergio Fernandez
. bimargulies Benson Margulies
. drew Drew Farris
. brock Brock Noland
. apurtell Andrew Purtell
Committers aldrin Aldrin Piri
. devriesb Brandon DeVries
. jcarey Jason Carey
. jbarnabee Jenn Barnabee
. joewitt Joseph Witt
. markap14 Mark Payne
. mcgilman Matt Gilman
. taftster Adam Taft
. tkurc Tony Kurc
. bbende Bryan Bende
. danbress Dan Bress
Incubation status reports
Incubation work items
Project Setup

This is the first phase on incubation, needed to start the project at Apache.

Item assignment is shown by the Apache id. Completed tasks are shown by the completion date (YYYY-MM-dd).

Identify the project to be incubated
date item
2014-11-24 Apache NiFi accepted by vote of the Incubator PMC.
Infrastructure
date item
2014-12-08 Ask infrastructure to create source repository modules and grant the committers karma.
2014-11-25 Ask infrastructure to set up and archive mailing lists.
2014-12-05 Ask infrastructure to set up issue tracker (JIRA, Bugzilla).
2015-05-28 Ask infrastructure to set up wiki (Confluence, Moin).
2014-12-08 Migrate the project to our infrastructure.
Mentor-related responsibility/oversight
date item
2014-12-01 Subscribe all Mentors on the pmc and general lists.
2014-12-01 Give all Mentors access to the incubator SVN repository. (to be done by the Incubator PMC chair or an Incubator PMC Member wih karma for the authorizations file)
2014-12-01 Tell Mentors to track progress in the file 'incubator/projects/{project.name}.html'
Verify distribution rights
date item
2014-12-29 Check and make sure that for all code included with the distribution that is not under the Apache license, we have the right to combine with Apache-licensed code and redistribute.
2014-12-29 Check and make sure that all source code distributed by the project is covered by one or more of the following approved licenses: Apache, BSD, Artistic, MIT/X, MIT/W3C, MPL 1.1, or something with essentially the same terms.
Establish a list of active committers
date item
2014-11-26 Check that all active committers have submitted a contributors agreement.
2014-12-01 Add all active committers in the STATUS file.
2014-11-26 Ask root for the creation of committers' accounts on people.apache.org.
Project specific
date item
2014-12-21 Update README with Export Control/ECCN Notice. Updated Apache ECCN XML. Send Export Control Notification.
Incubation

These action items have to be checked for during the whole incubation process.

These items are not to be signed as done during incubation, as they may change during incubation. They are to be looked into and described in the status reports and completed in the request for incubation signoff.

Collaborative Development
  • Have all of the active long-term volunteers been identified and acknowledged as committers on the project?
  • Are there three or more independent committers? (The legal definition of independent is long and boring, but basically it means that there is no binding relationship between the individuals, such as a shared employer, that is capable of overriding their free will as individuals, directly or indirectly.)
  • Are project decisions being made in public by the committers?
  • Are the decision-making guidelines published and agreed to by all of the committers?
Licensing awareness
  • Are all licensing, trademark, credit issues being taken care of and acknowleged by all committers?
Project Specific

Add project specific tasks here.

Exit

Things to check for before voting the project out.

Organizational acceptance of responsibility for the project
  • If graduating to a new PMC, has the board voted to accept it? YES July 15 2015
Incubator sign-off
  • Has the Incubator decided that the project has accomplished all of the above tasks? YES. June 2015.