Apache Beehive Incubation Status
Apache Beehive Project Incubation Status

This page tracks the project status, incubator-wise. For more general project status, look on the project website .

Description

The Beehive project is an extensible Java application framework with an integrated metadata-driven programming model for web services, web applications, and resource access. The framework leverages the latest innovations in the forthcoming JDK 1.5, particularly JSR 175 metadata annotations. It currently builds on key Apache projects such as Tomcat, Struts, MyFaces, and Axis.

While this proposal focuses on a framework consisting of these three subprojects, it is expected that the Apache community will come up with additional innovative ideas that will evolve into future subprojects. The currently planned components include:

News
Project info
Detailed References:
Item Type Reference
Website www http://incubator.apache.org/beehive/
. wiki http://wiki.apache.org/beehive
Mailing list dev beehive-dev@incubator.apache.org
. user beehive-user@incubator.apache.org
. commits beehive-commits@incubator.apache.org
. ppmc beehive-ppmc@incubator.apache.org
Bug tracking . JIRA: Beehive (BEEHIVE), Admin: Heather Stephens (heathers)
Source code SVN http://svn.apache.org/repos/asf/incubator/beehive
Proposal wiki http://wiki.apache.org/incubator/BeehiveProposal
Mentor craigmcc Craig R. McClanahan
Committers ias Changshin Lee
Committers cjudson Chris Judson
Committers cliffs Cliff Schmidt
Committers craigc Craig Crutcher
Committers dolander Daryl Olander
Committers dims Davanum Srinivas
Committers davidbau David Bau
Committers dmkarr David M. Karr
Committers daveread David Read
Committers ekoneil Eddie O'Neil
Committers heathers Heather Stephens
Committers jongjinchoi Jongjin Choi
Committers kylem Kyle Marvin
Committers jsong James Song
Committers kentam Ken Tam
Committers mclark Michael Clark
Committers rich Richard Feit
Committers rotan Rotan Hanrahan
Committers scottryan Scott Ryan
Committers steveh Steve Hanson
Committers stocco Steven Tocco
Committers vsalvato Vince Salvato
Committers mmerz Mike Merz
Committers hattori Fumitada Hattori
Committers bryanche Brian Che
Incubation status reports

2005-04-26

Beehive is in the home stretch of its 1.0-level release; we declared a beta release in March, and are on track to deliver a 1.0 in the late May timeframe. Posting automated daily builds continues to be an challenge, but otherwise infrastructure is well in place. At this point we are largely focused on fit'n'finish issues in the code, as well as a polished set of samples and documentation.

The Beehive community added Bryan Che as a new committer in February, 2005. With the beta release and open planning on features for the next version, we are seeing increased dev/user list activity -- we anticipate that the 1.0 release will be even more significant in building the community, and hope to graduate from the Incubator sometime soon after the 1.0 release. Certain Beehive components have a very clear affinity with the Apache Struts and AXIS projects, and those projects may play a role in graduation (pending further discussion).

2004-10-18

Code & Infrastructure

Legal
Community
Release Plans




Incubation work items
Project Setup

This is the first phase on incubation, needed to start the project at Apache.

Item assignment is shown by the Apache id. Completed tasks are shown by the completion date (YYYY-MM-dd).

Identify the project to be incubated
Date Item
DONE - ....-..-.. Make sure that the requested project name does not already exist and check www.nameprotect.com to be sure that the name is not already trademarked for an existing software product.
N/A If request from an existing Apache project to adopt an external package, then ask the Apache project for the cvs module and mail address names.
N/A If request from outside Apache to enter an existing Apache project, then post a message to that project for them to decide on acceptance.
DONE - 2004-07-15 If request from anywhere to become a stand-alone PMC, then assess the fit with the ASF, and create the lists and modules under the incubator address/module names if accepted.
Interim responsibility
Date Item
DONE - 2004-05-09 Identify all the Mentors for the incubation, by asking all that can be Mentors.
DONE - 2004-06-15 Subscribe all Mentors on the pmc and general lists.
DONE - 2004-07-16 Give all Mentors access to all incubator CVS modules. (to be done by PMC chair)
DONE - 2004-07-18 Tell Mentors to track progress in the file 'incubator/projects/{project.name}.html'
Verify distribution rights
Date Item
DONE - 2004-10-18 Check and make sure that for all code included with the distribution that is not under the Apache license, we have the right to combine with Apache-licensed code and redistribute.
DONE - 2004-10-18 Check and make sure that all source code distributed by the project is covered by one or more of the following approved licenses: Apache, BSD, Artistic, MIT/X, MIT/W3C, MPL 1.1, or something with essentially the same terms.
DONE - 2005-05-04 BEA completes code grant for the "system control" source code from ControlHaus to be added to the Beehive SVN repository and released with our distributions.
Establish a list of active committers
Date Item
DONE ....-..-.. Check that all active committers have submitted a contributors agreement.
DONE - 2004-07-14 Add all active committers in the STATUS file.
DONE - 2004-07-18 Ask root for the creation of committers' accounts on cvs.apache.org.
2004-12-17 Added Fumitada Hatori (Wolfgang) as a committer.
2005-02-07 Added Bryan Che a committer.
Infrastructure
Date Item
DONE - 2004-07-15 Ask infrastructure to set up and archive Mailing lists.
DONE - 2004-07-16 Ask infrastructure to create source repository modules and grant the committers karma.
DONE - 2004-07-16 Decide about and then ask infrastructure to setup an issuetracking system (JIRA).
DONE - 2004-07-16 Migrate the project to our infrastructure.
Project specific

Add project specific tasks here.

Incubation

These action items have to be checked for during the whole incubation process.

These items are not to be signed as done during incubation, as they may change during incubation. They are to be looked into and described in the status reports and completed in the request for incubation signoff.

Collaborative Development
  • DONE - Have all of the active long-term volunteers been identified and acknowledged as committers on the project?
  • DONE - Are there three or more independent committers? (The legal definition of independent is long and boring, but basically it means that there is no binding relationship between the individuals, such as a shared employer, that is capable of overriding their free will as individuals, directly or indirectly.)
  • DONE - Are project decisions being made in public by the committers?
  • DONE - Are the decision-making guidelines published and agreed to by all of the committers?
Licensing awareness
  • DONE - Are all licensing, trademark, credit issues being taken care of and acknowleged by all committers?
Project Specific Tasks

Add project specific tasks here.

Exit

Things to check for before voting the project out.

Organizational acceptance of responsibility for the project
  • If graduating to an existing PMC, has the PMC voted to accept it?
  • If graduating to a new PMC, has the board voted to accept it?
Incubator sign-off
  • Has the Incubator decided that the project has accomplished all of the above tasks?